- October 2005 Purchase and Sale Agreement for CMF finalized
- December 2005-March 2006 CMF Site Grading Work
- June 2006-July 2007 ECMF Building Construction
- August 2006-December 2006 Phase-1 Canyon Road Construction
- September 2006-March 2008 CMF Building Construction
- January 2007-December 2007 Phase-2 Canyon Road Extension
- Fall 2007 ECMF Grand Opening
- Late Fall 2007 196th Street East Construction
- Spring 2008 CMF Grand Opening
|
|

|
|