pierce county logo Pierce County mount rainier left mount rainier mount rainier left
Public Works and Utilities
horizontal page banner


D411 - Woodland Creek Drainage Improvements



Project Engineer/Manager
Al Zehni, P. E.
253-798-4677

Design Engineer
Jeffrey Davidson
253-798-3090

What is the Woodland Creek Drainage Improvements Project?

Project Objectives

  • Alleviate poor drainage along Woodland Avenue between a detention pond outlet north of 123rd Street East and 102nd Street East.

  • Reduce erosion along Woodland Creek. Residents along Woodland Creek have reported channel erosion since 1993. Erosion damages land and degrades aquatic habitat. Sediment fills in the floodplain downstream.

Why is the Project Needed?

Flooding of Woodland Avenue between 123rd Street East and 102nd Street East occurs due to a rural street drainage system. As homes were built, culverts were placed under driveways. In side view the elevation of culverts creates a zigzag pattern. Some of the culverts have adverse grades (outlets are higher than the inlets).

A low culvert between two higher culverts can trap water, creating a partial obstruction and a backwater effect. Backwater is a pooling of water behind an obstruction. It can lead to flooding.

The detention pond at 112th cannot drain properly because of the inability of the Woodland Avenue drainage system to the north to drain low flows. Woodland Avenue's eastern ditch holds approximately a foot of water before it starts flowing and takes up room in the ditch needed for conveying stormwater. This causes water needing to exit the detention pond to back up into the pond, instead of draining away.

Woodland Creek channel is eroding severely north of 93rd Street East. During storms high volumes of stormwater in the creek and steep grades have eroded deep cuts and destabilized stream banks. This erosion creates sediment that destroys fish habitat downstream. Photo1 and Photo 2.

Project Alternatives

Map

- Create positive drainage along Woodland Avenue and install an energy dissipater at the downstream end of the 84th Street East culvert. Adjust the existing ditch profile along Woodland Avenue from 116th to 104th Street East to allow low water flows to drain. Replace several culverts. Culverts would not be enlarged so volume is not increased. Realign the drainage ditch and pipelines to improve drainage. Install an energy dissipater at the 84th Street East culvert out to lessen erosion at that location. Estimated cost: $500,000.


PROS CONS
Less Costly Postpones cost of building additional stormwater detention to a later date.
Makes the existing detention ponds more effective Does not address long-term detention needs
Least traffic disruption
Reduces erosion at 84th Street East Erosion at other locations not addressed

- Construct a detention pond in the vicinity of SR-512 (between 112th and 102nd). The Clear/Clarks Creek Basin Plan calls for construction of an additional detention pond in the Woodland Creek drainage area to reduce the volume and velocity of stormwater runoff in Woodland Creek. Detention would reduce stream channel erosion. Estimated cost: $1,500,000.

PROS CONS
Provides detention now when less costly High cost
Additional basin detention provided Streambank stabilization at 84th not addressed
Reduces peak flows in the creek and erosion potential of the creek Very erosive peak flows remain discharged to Woodland Creek
Would not eliminate flooding on Woodland Ave.

- Construct a bypass pipeline. Even with additional detention, the volume of stormwater during severe storms will erode the Woodland Creek channel and potentially undermine retaining walls next to the creek. This can be avoided by laying a bypass pipeline from the pond outlet down Woodland Avenue to a point near 80th Street East. Estimated cost: $2,500,000.

PROS CONS
Highest cost
Peak flows in Woodland Creek routed around high erosion area No additional basin detention provided
Protects property adjacent to the creek Greatest traffic disruption
Eliminates need for driveway culvert replacements at 72nd Ave East Would not eliminate flooding on Woodland Avenue

Points of Contact:


Al Zehni, P.E. Project Manager
Pierce County Public Works & Utilities, Surface Water Management Division
2702 South 42nd Street
Tacoma, WA 98409
(253) 798-4677
azehni@co.pierce.wa.us

Jeffrey Davidson, Design Engineer
Pierce County Public Works & Utilities, Surface Water Management Division
2702 South 42nd Street
Tacoma, WA 98409
(253) 798-3090
jdavidso@co.pierce.wa.us

Marsha Huebner, Permits and Planning
Pierce County Public Works & Utilities, Surface Water Management Division
2702 South 42nd Street
Tacoma, WA 98409
(253) 798-4662
mhuebne@co.pierce.wa.us

Clear/Clarks Creek Basin Plan Projects for Woodland Creek Drainage Basin

Table 9.13 WOODLAND CREEK Recommended CIPs

ID Project
Name
Project
Score
Estimated
Cost
Priority
WO-RST01 Woodland Creek
Stream Corridor Restoration
265 Segment 1: 490,000
Segment 2: 490,000
Segment 3: 490,000
TOTAL: 1,470,000
High
WO-SBS01 Woodland Creek
Streambank Stabilization
at 84th Street East
150 305,000 Medium
WO-SBS02 Woodland Creek Stream
Bank Stabilization at
80th Street E
142 357,000 Medium
WO-DP01 Woodland Avenue
Flood Control Phase II
155 2,960,000 Medium
WO-CR02 Woodland Creek
80th Street East
Culvert Replacement
88 27,000 Low
WO-CR01 Woodland Creek
& 72nd Avenue
East Culvert
Replacement Project
- 93rd Street East to
96th Street East
105 102,000 Low
Total Estimated Cost for Woodland Creek CIPs $5,221,000

Projects highlighted in grey are related to the Woodland Creek Drainage Improvement Project.

Project Timeline 2008

  • Scoping Project 2008
  • Public Meeting on Alternatives 2008
  • Decision on Preferred Alternative 2009
  • Detailed Design & Application for Permits 2010
  • Construction

Pierce County Ferry
Schedule, fares, and more.

Track our Progress
View our budget performance charts.

PC Responds
Stop illegal dumping.

Request Road Maintenance
(253) 798-6000

Report Downed Signs
(253) 531-6990
Privacy Policy | Text Only Version | Webmaster

Copyright © 1996-2009 Pierce County Washington. All rights reserved.
             
Last Modified
May 8 2009 3:06PM