pierce county logo Pierce County mount rainier left mount rainier mount rainier left
Public Works and Utilities
horizontal page banner


McCormick Creek Fish Barrier

McCormick Creek Culvert Replacements, Burnham Drive East, Woodhill Drive East
Click on picture to enlarge
D180 - McCormick Creek Culvert Replacements - Burnham Dr. E and Woodhill Dr. E.

Project Engineer/Manager
Helmut Schmidt
253.798.6164

Environmental Biologist
Ann Boeholt
253.798.4694

Contractor
Thompson Brothers Excavating
18211 NE Forth Plain Rd
Vancouver, WA 98682

Construction: Summer of 2006


For ease of download and viewing, documents on this webpage are available as Adobe Acrobat PDF files.

Burnham Drive Crossing:
Replace Concrete Culvert Pipes with a 12 foot wide Concrete Arch Culvert to improve fish passage and reduce the risk of roadway flooding.

Before

After

Woodhill Drive Crossing:
Remove the existing fish barrier and construct log weir fish ladders to improve fish passage.

Before

After

UPDATE:

The McCormick Creek Culvert Improvements Project started on July 11th with the closure of Burnham Dr. in the vicinity of Woodhill Dr. A new box culvert was installed under the road and the road re-opened July 21st.

Pierce County employee?s and a WDFW biologist captured and transported over 50 fish around the proposed Burnham Drive work zone prior the removal of the existing culverts. The fish were placed back into McCormick creek downstream of the work area. The fish were primarily native cutthroat trout as large as 5 inches long.

The second phase of the project began on August 8. The second phase is to install 5 timber and bolder wiers to raise the water surface elevation of a plunge pool, thereby removing the fish passage barrier of the hanging culvert downstream of Woodhill Drive. Among the first tasks with this project was fish salvage and dewatering of the instream work area. We captured and transported a total of 89 cutthroat trout fingerlings, 22 coho salmon fingerlings, as well as a handful of brook lamprey and 1 sculpin within this reach of stream.

The project is expected to be complete by August 17th. Construction phase is completed. Planting to start in late October 2006.

Overview:

Scope of Work

Burnham Project Plan:

Preliminary Plan Sheet

Woodhill Project Plan:

Preliminary Plan Sheet

Project Timeline (Dates are approximate):

Final Plans and Specifications for Bid: June 15, 2005
Construction Notice to Proceed: June 15, 2006
Construction Completed: October 15, 2006

Project Cost:

$450,000 - $500,000

Pierce County Ferry
Schedule, fares, and more.

Track our Progress
View our budget performance charts.

PC Responds
Stop illegal dumping.

Request Road Maintenance
(253) 798-6000

Report Downed Signs
(253) 531-6990

Privacy Policy | Text Only Version | Webmaster

Copyright © 1996-2008 Pierce County Washington. All rights reserved.
             
Last Modified
Dec 20 2007 12:02PM