121st Street South (C St S to SR7) (CRP 5878)

What’s happening

Bike lanes and sidewalks will be added to 121st Street South from C Street South to State Route 7 during a project that is expected to start July 15. The work expected to be complete in early October.


The project area is located near Pacific Lutheran University in Parkland. 


Work hours will be 7 a.m. to 3:30 p.m. The road may be reduced to one lane with alternating traffic during work hours. Access for pedestrians and bicyclists will be maintained.


Image of the project vicinity map.
Image of the project.

About the Project

The road shoulders will be widened to accommodate paved bike lanes, curbs, gutters, sidewalks and landscaping.


A marked crosswalk with a pedestrian-activated flashing beacon will be added approximately 50 feet west of the Pierce Transit transfer station. 


Street lights will also be added, along with an enclosed storm drainage system and stormwater treatment facilities.


Image of the project roadway section.
Image of project Right-of-Way Plans cover sheet.

Construction schedule

Crews will remove vegetation and debris from the project area July 15.


From mid-July to mid-August, crews will install the enclosed storm drainage system. Next, the crews will install the curbs, gutters, sidewalks, street lights and crosswalk from mid-August to early September. 


Crews will pave the roadway in September. Late in the month, crews will clean up the site and add landscaping. In early October, the flashing beacon will be activated, and the road, crosswalk and bike lanes will be striped. 


The project’s contractor is Axum General Construction Inc. The construction cost is approximately $821,000. This project is funded with federal Surface Transportation Program (Urban) funds and County Road Funds.


Project Timeline


May 15, 2020: Bid Opening date


June 2, 2020: Pierce County awarded the contract to Axum General Construction Inc.


June 4, 2020: Pierce County hosted the Pre-Construction Meeting


July 15, 2020: Anticipated Notice to Proceed


Early October 2020: Construction expected to be complete

Contact Us
Send a message arrow
Andrew Davis, P.E.
Construction Supervisor
Phone: (253) 798-6913
Address:
2702 S 42nd St., Suite 109
Tacoma, WA 98409