Fairfax Forest Reserve Road East (CRP 5861)

What's Happening


Engineering: 

We’re planning repairs and replacements of 2 miles of Fairfax Forest Reserve Road East between Poch Creek and the Mount Rainier National Park Carbon River Entrance.  Improvements being considered include:

  • Installing guardrail.
  • Upsizing 7 existing culverts.
  • Adding 4 new culverts.
  • Resurfacing the existing road.

Land:  All work will be on National Forest and National Parks land or County road right of way.

Survey:  County staff will be gathering field data of the project area.

Project Timeline

August 2018 to Spring 2024: Gathering of field data, design engineering, environmental permitting.

2024: Construction.
Contact Us
Send a message arrow
Patrick Baughman, P.E., PMP
Design Supervisor
Phone: (253) 798-3157
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409