Bridge #31221-A - Cramer Road NW / Glencove (5871)

What's Happening


Engineering: Pierce County has completed a field survey and is in the preliminary design stage.

Land: Right-of-Way needs will be evaluated.

Environmental: Necessary environmental permits will be obtained.

About the Project


Planned improvements to Cramer Road Northwest at its crossing with Glencove (CRP 5871) are intended to improve safety and replace the existing bridge, including the following:
  • Remove the existing bridge.
  • Reconstruct a new bridge and approach roadways.
  • The new bridge will be two lanes with paved shoulders and constructed with pre-tensioned precast concrete girders.
  • Cramer Road Northwest will be closed during construction.

Project Timeline

Fall 2018 to Winter 2019: Surveying, preliminary engineering and right-of-way plans. 

Winter 2019 to Spring 2023: Right-of-way acquisition, environmental documentation, construction plans, specifications and estimates.

Summer to Fall 2023: 
Construction

Fall 2023: Open to traffic.