950 Building Multiple Projects

2nd Floor Restrooms


Restroom improvements include:

  • Updating plumbing, fixtures and finishes
  • Adding a single ADA restroom
  • Adding a single lactation room

*Preliminary Construction Schedule

Demolition 

•    Phase I (North Restrooms) – 10/14/2019 to 10/25/2019

•    Phase II (Single Restrooms) -11/25/2019 to 11/29/2019

Interior Framing & Rough-In of Electrical, Mechanical and Plumbing

•    Phase I (North Restrooms)– 10/25/2019 to 11/15/2019

•    Phase II (Single Restrooms) – 11/30/2019 to 12/06/2019

Finishes, Doors, Hardware, Trim & Misc. Specialties

•    Phase I (North Restrooms)– 11/15/2019 to 11/22/2019

•    Phase II– 12/07/2019 to 12/13/2019

Final Inspections, Furniture, & Occupancy 

•    Phase I (North Restrooms) – 11/23/2019 to 11/24/2019

•    Phase II (Single Restrooms)– 12/14/2019 to 12/15/2019

*A tentative schedule will be finalized soon and updated regularly during the project.

  1. North Restroom
  2. West Restroom

North Restroom

Before construction.

More Information

For more information on this project, please email Construction Project Manager, Diane Cooksey.

About the Contractor

Olympic Pen Logo

The mission of Olympic Peninsula Construction, Inc. is to attract and complete commercial and industrial construction projects in a manner that focuses on profit, quality and professionalism while having a positive impact on all with whom we come in contact.

HVAC & 2nd Floor Fire Sprinkler


This project includes:

  • Replacing the building's existing HVAC system
  • Installing a 2nd floor fire sprinkler system
  • Improvements to the 2nd floor conference room

*Preliminary Construction Schedule

Phase I 

Third Floor 1A – 10/14/2019 to 11/13/2019

  • Staff relocates to second floor
  • Demo third floor South
  • Structural work
  • Install HVAC
  • Staff moves back third floor

Third Floor 1B – 11/13/2019 to 12/6/2019

  • Staff relocates to second floor
  • Demo third floor North
  • Install HVAC
  • Staff moves back third floor

Phase II 

Second Floor 2A – 12/6/2019 to 12/26/2019

  • Demo second floor South
  • Install HVAC

Second Floor 2B – 12/27/2019 to 1/22/2020

  • Staff relocates to second floor South
  • Demo second floor North
  • Install HVAC and Fire Sprinklers
  • Staff moves back third floor

Phase II

1st Floor – 1/22/2020 to 2/14/2020

  • Staff relocates to second floor
  • Demo 1st floor
  • Install HVAC
  • Staff moves back

Phase IV 

Basement – 2/14/2020 to 3/8/2020

  • Demo Phase
  • Install HVAC

*A tentative schedule will be finalized soon and updated regularly during the project.