Engineering: Pierce County has completed the project kick off meeting and is completing a field survey.
Land: Right-of-way needs will be evaluated.
Environmental: Necessary environmental permits will be obtained as needed.
About the Project
Planned improvements to Markham Avenue Northeast at approximately 1,250 feet W/O SR 509 (CRP 5839) are intended to repair or replace the failing retaining wall. Markham Avenue Northeast may have partial to full road closures during the project.
Project Timeline
Early 2020 to Fall 2021: Surveying, preliminary engineering and right-of-way plans.
Fall 2021 to Spring 2022: Right-of-way acquisition, environmental documentation, construction plans, specifications and estimates.