Bridge Deck Rehabilitations - Various Locations (CRP 5864)

What’s Happening

Engineering: Pierce County is in the preliminary design stage.


Land: All improvements are expected to fit within the existing right-of-way.


Environmental: Necessary environmental permits will be obtained as needed.

Group 1

Image of the project vicinity map.
Image of project photo.

Group 2

Image of the project vicinity map.
Image of project photo.

Group 3

Image of the project vicinity map.
Image of project photo.

About the Project

The project involves resurfacing bridge decks at various locations throughout the County. The locations include:


Group 1:Bridge #12173-B (304th Street East at South Fork Muck Creek crossing)
Group 2:Bridge # 33206-A (Sumner Buckley Highway at PSE Canal crossing)
Group 3:Bridge #17173-A (16th Avenue East at Lacamas Creek crossing)

Project Timeline

Spring 2020: Begin preliminary engineering, development of construction plans, specifications, and estimates.


Fall 2020 to Spring 2021: Begin construction.

Contact Us

Kraig Shaner, P.E.

Bridge Supervisor

Phone: (253) 798-2764

Address:

2702 S 42nd Street, Suite 109

Tacoma, WA 98409